Both McDonald’s and Chick-fil-A needed to ensure new restaurants could open on their scheduled launch dates. A critical part of this was the timely delivery of Openreach infrastructure. Without seamless connectivity in place, store operations, payment systems, and customer service would be severely impacted.
However, working with statutory bodies presents several challenges, from securing engineer attendance on site to ensuring new addresses are correctly allocated. As former Openreach employees, AH Connections bring direct links and insider knowledge, enabling us to navigate these processes efficiently and overcome common delays.
The Challenge
AH Connections were appointed to take full ownership of the telecoms infrastructure element, ensuring early engagement with Openreach to mitigate delays. Acting as the single point of contact, we coordinated directly with contractors and the client, providing end-to-end project management across both offsite planning and onsite delivery in collaboration with the main contractor.
The Solution
AH Connections delivered the telecoms infrastructure on time and without disruption. Early engagement with Openreach and streamlined project management ensured each restaurant opened as scheduled, fully connected and operational from day one.
Project Outcome
‘I’ve had no issues with how AH Connections manage things and are already making the process quicker and easier than the other providers we have used.’
‘Great work as always Anthony and Ellie, you ensure the restaurants open ontime and any issues are raised early’
Testimonial
Working with:
End user
Contractor
Infrastructure provider
Scope of works
Appointed by Levertech Engineering Services, AH Connections were tasked with splicing and testing the fibre optics cables installed by the principal contractor at the new Royal Mail depot located in Warrington.
Objectives
✓ Survey site and supply costs
✓ Set up & splice 18 x 12 core multi mode fibre cables
✓ Testing to industry standards utilising a Fluke DSX500
Challenges
✓ Ability to work to critical timescales
✓ Attend site with 24 hours notice
✓ Keeping the client running throughout without disruption to business
Project Outcome
The project was delivered on time, within customer time frames and without the need for any extras or additions to the initial quote. All testing was carried out on site before handover with test results supplied to the customer contact.
‘Working with AH Connections was straightforward, we had a tight timescales with our client and they managed to survey and attend site within 48 hours. They were able to complete works in a timely manner and work to the end users timescales and standards’
Allen Rutherford, Levertech Engineering Services Ltd